Archive for August, 2018

Intrusive Construction Complete at Wills Wharf

Intrusive construction work on the Area 1 portion of the Wills Wharf site has been completed.  The geomembrane liner (part of the environmental cap) has been closed and all air monitoring for hexavalent chromium has ceased for this portion of the site. Work continues “off-cap” where air monitoring for dust…

Read More

Pump Station Nearing Completion

The pump station structure at the corner of Caroline and Point Streets is nearly finished, with an estimated 6-8 weeks remaining until completion. This new pump station is a vital piece of infrastructure that fully ties the new buildings at Harbor Point into established Baltimore City sewage lines. Ultimately, the…

Read More

WeWork to Open First Baltimore Location at Harbor Point

WeWork will be opening its first Baltimore location in 2020 at Harbor Point. The coworking space provider will take two floors at Wills Wharf, currently under construction, and is expected to accommodate a community of more than 1,100 members. “WeWork is thrilled to contribute to an innovative and thriving technology…

Read More

Jellyfish Relocating to Harbor Point

Beatty Development Group and Armada Hoffler Properties announced today that Jellyfish, a UK-based digital marketing agency, has signed an office lease at Wills Wharf, the next mixed-use building set to deliver at Harbor Point. Jellyfish opened its U.S. headquarters in Baltimore in 2014 and will relocate from its current location at 250…

Read More